Alpha T&D
Programme Tracker
CT3411 ยท PA Energy / SPEN ยท Clause 32
Connecting...
Thornton North Network Rail Project (275/25KV) CT3411 Clause 32 Updated 13/05/26 68% overall Phase 1 SGT3 โ€” 84% Phase 2 SGT4 โ€” 29% 5 CEs to raise
โ€”
โš  Commercial flags:
CE Control & Fuse box โ€” long delay (PA to supply)
CE Above ground earthing โ€” delivery delay
CE BB & Clamps โ€” supply delay
CE Terminate C&P โ€” additional DC works
EWN0002/TQ0004 NCT Link Box & VT Fuse Boxes not ordered
EWN0007 275kV CB
68%
Overall progress
84%
Phase 1 SGT3
29%
Phase 2 SGT4
39%
DPD works
5
CEs to raise
04 Dec
Completion
Phase 1 SGT3 (actual)
84%
Phase 2 SGT4 (actual)
29%
Thornton North DPD
39%
Key: Complete In progress Delayed Critical / 0% Baseline Milestone CE flagged